Posts Tagged ‘building your first home’

Porches Formed and ready for pour

Posted on the June 17th, 2009 under First Stages by admin

I visited the site today and discovered that the porches were being formed and prepared for concrete pour scheduled for Monday 6-22-2009. I also noticed that the porta-potty had arrived on site. Now the workers will not have to leave to use the restroom. :) I need to be certain that the block crew fixes the damage to the stem wall prior to pouring the slab. This is becoming a concern for me. In order to pass an inspection the wall must be fixed and I am sure it will get done, I just want to know when so I don’t lose any sleep over it. Ha Ha.

Back Porch Shown. Size: 11' x 22' Should make for some nice BBQ's

Back Porch Shown. Size: 11' x 22' Should make for some nice BBQ's

Foundation Steel Installed today

Posted on the June 7th, 2009 under First Stages by admin

Today all of the steel for the stem wall footings was installed. The steel is to ensure structural integrity throughout the foundation. Without the steel, the foundation would be extremely weak. Check out the photos. We are getting closer to concrete!

dscn1942 dscn1941 dscn1940

dscn1939 dscn1934 dscn1937

dscn1935 dscn1932 dscn1931

dscn1928 dscn1927 dscn1926

dscn1925 dscn1924 dscn1922